I-16/I-75 interchange improvements in Macon-Bibb County set for next week

Webp 2hlp9i79im6y705zdt2npp6guhgi

Russell R. McMurry, P.E., Commissioner | Georgia Department of Transportation

Russell R. McMurry, P.E., Commissioner | Georgia Department of Transportation

Contractors for the Georgia Department of Transportation (GDOT) will continue work on the I-16/I-75 Interchange Improvement Project in Macon-Bibb County from March 14 to March 21, 2025. The construction activities are contingent upon weather and on-site conditions.

From Tuesday, March 18 through Thursday, March 20, lane closures and traffic shifts will occur between 9 p.m. and 5 a.m. each night. Law enforcement vehicles will slow traffic on I-16 eastbound between the interchange and the exit at Martin Luther King Jr Boulevard/Coliseum Drive as crews work on a newly constructed bridge over the exit off-ramp.

There are ongoing long-term closures affecting Spring Street's far right lane at the I-16 westbound on-ramp, which has been relocated to the far left lane.

The scheduled construction activities include:

Phases 4 and 5: Work continues from I-16 westbound/I-75 to Walnut Creek with ongoing construction of bridge substructures and superstructures for entrance and exit ramps, new Second Street bridge substructure, two new I-16 eastbound bridge substructures, pouring deck spans and edge beams on new structures, demolition of an existing ramp to I-16 eastbound, construction of retaining walls along I-75 northbound and southbound, as well as installation of drainage systems throughout the project area.

Phase 2 and 3: Along I-75 from Hardeman Avenue to I-16 eastbound, lighting installations continue at Riverside Bridge and Walnut Street. Construction of sound and visual walls along both directions of I-75 is also underway.

Phase 1: Evaluation is ongoing for remaining work items from the split at I-16/I-75 to Martin Luther King Jr. Boulevard exit.

This $500 million megaproject aims to enhance safety and mobility by widening and reconstructing sections of I-16, I-75, their interchange in Macon-Bibb County through seven phases that extend until 2030. Once completed, it promises improved lanes, upgraded bridges, better drainage systems among other enhancements benefiting local commuters as well as regional travelers.

Motorists should expect delays due to these works; caution is advised when traveling through affected zones. For real-time updates on traffic conditions or work status call 511 or visit GDOT’s online platforms including their app "Georgia 511."

"Georgia Department of Transportation plans constructs maintains Georgia’s state federal highways involved bridge waterway public transit rail general aviation bike pedestrian programs help local governments maintain roads," stated GDOT representatives emphasizing their commitment towards innovation safety sustainability mobility aiming boost competitiveness leadership transportation.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS